- River Street intersection south of the bridge:
- Another crew scheduled to mobilize Monday and start pavement & sidewalk removals at the intersection
- Crew will then start water and sewer work, including boring water main under the river on the west side of the bridge
- WIS 23 Flagging 8am-7pm all week as necessary – EXPECT DELAYS
- East River St will be CLOSED at WIS 23 starting Monday, April 12 thru Friday, May 7
- Bridge to Ann Street:
- Pipe crew will continue sanitary sewer and water main installations
- Alice St will remain CLOSED at Main St all week - access to Casey’s will remain open to/from Alice St, just east of the barricades
- Water service replacements may start later in the week – 48 hour notification will be given to property owners for planned water outages
- Ann Street to Harriet Street:
- Crew may start removing pavement and sidewalk on the east side of Main Street, especially if there is a rain day and they can’t work on water & sewer
- Side street access will remain open
- Harriet Street to Minerva Street:
- No work planned
Upcoming & Other information:
- CTH F / West River St will be CLOSED at WIS 23 starting Monday, April 19 thru Friday, May 7 – emergency vehicle access only
- The Contractor has piled a load of the underlying pavers/bricks at the City’s Shop on Spring Street that are free for the taking - more will be dropped off if there is a high demand