- Bridge to Ann Street:
- Continue pavement and sidewalk removal on the east side of Main St
- Sidewalk next to buildings will remain in place for pedestrians
- Pipe crews will mobilize to start installing water main and sanitary sewer in front of Casey’s
- Tuesday, April 6th thru Friday, April 9th – flaggers controlling Main St traffic for crews to install water & sewer across the west side north of the bridge - expect delays
- No water service disruptions anticipated next week
- Alice St access to/from Main St will remain CLOSED all week
- Access to Casey’s will remain open to/from Alice St, just east of the barricades
- Ann Street to Harriet Street:
- Monday, April 5th – Remove street lights on the east side of Main St
- Contractor planning to leave pavement in place for a couple weeks while pipe crews work from the bridge up to Ann St
- Harriet Street to Minerva Street:
- Tree removal
- WIS 23 will be CLOSED early next week for tree removal only
- Barricades will be staggered to maintain local access to properties within the work zone only
- When tree removal is completed, this section will be re-opened
- Access to Lucy St & Washington St on east side of WIS 23 may CLOSE for crews to start working on sanitary sewer in this area
- River Street intersection south of the bridge:
- Crew may start removing pavement at the intersection Tuesday or Wednesday
- Flaggers controlling traffic at the intersection – expect delays
- East River St access to/from WIS 23 will be CLOSED